Declaration of Progress of Loans and Interest Repayment
= Translation =
Ref: CK-08-000-AFD-L-0056
12 March 2008
Subject: Declaration of Progress of Loans and Interest Repayment
Attention: President
The Stock Exchange of Thailand
Ref:1) The Company's Letter No. CK-07-0000-AFD-L-0226 dated 25 April 2007
2) The Company's Letter No. CK-07-0000-AFD-L-0164 dated 29 May 2007
3) The Company's Letter No. CK-07-0000-AFD-L-0297 dated 27 December
2007
4) The Company's Letter No. CK-07-0000-AFD-L-0584 dated 28 December
2007
Reference is made to the fact that CH.Karnchang Public Company
Limited "Company" has issued a declaration letter of the additional
information of the consolidated financial statements ended 31 December 2006 on
loans in item 11(in proportion to the company's interest in the joint-
venture) of the Notes to Consolidated Financial Statements of the Company
as followed.
1) Joint Venture CKAE Consortium as planned to receive a totaled loans
repayment within no later than 31 December 2008.
Unit : Million Baht
Best Plan Modern Construction
Technology Co., Ltd. Material Co., Ltd.
Principal Interest Principal Interest
First loan 24.5 - 24.5 -
Loans during first
loan-end of 2006 239.7 84.7 423.1 148.1
Receivable repayment during
first loan-end of 2006 (54.5) (19.8) (55.6) (90.9)
Balance as of
31 December 2006 209.7 64.9 392.0 57.2
Interest during the period - 30.6 - 54.7
Repayment during the period - - - -
Balance as of 31 March 2007 209.7 95.5 392.0 111.9
Repayment as planned
(30 April 2007) - (19.8) - -
Balance 209.7 75.5 392.0 111.9
Unit : Million Baht
Best Plan Modern Construction
Technology Co., Ltd. Material Co., Ltd.
Principal Interest Principal Interest
Interest during the period - 6.7 - 11.4
Repayment during the period - (25.7) (260.3) (123.1)
Balance as of 31 July 2007 209.7 56.7 131.7 0.2
Interest during the period - 5.0 - 3.1
Repayment during the period - (19.8) (5.9) (1.0)
Balance as of 31 October 2007 209.7 41.9 125.8 2.3
Interest during the period
of November 2007 to
February 2008 - 6.6 - 1.3
Repayment during the period - - (113.7) (3.3)
Balance as of
29 February 2008 209.7 48.5 12.1 0.3
2) Joint Venture CKET Consortium as planned will receive at least a half
of loans repayment within no later than 31 December 2008 and the rest will be
paid totally within 30 June 2009.
Rayong Real Private Inter
Estate Co., Ltd Construction Co., Ltd.
Principal Interest Principal Interest
First loan 152.0 - 160.0 -
Loans during first
loan-end of 2006 1,048.0 231.9 44.0 29.9
Receivable repayment during
first loan-end of 2006 (79.1) (25.6) (60.6) (12.1)
Balance as of
31 December 2006 1,120.9 206.3 143.4 17.8
Interest during the period - 70.4 - 9.1
Repayment during the period - - - -
Balance as of
31 March 2007 1,120.9 276.7 143.4 26.9
Repayment during
April 2007 - - - -
Balance as of
31 March 2007 1,120.9 276.7 143.4 26.9
Interest during the period - 32.6 - 4.1
Receivable repayment
during the period - (170.5) - (24.2)
Balance as of 31 July 2007 1,120.9 138.8 143.4 6.8
Interest during the period - 24.4 - 3.1
Repayment during the period - (14.6) (0.7) (7.5)
Balance as of
31 October 2007 1,120.9 148.6 142.7 2.4
Interest during the period
of November 2007 to
February 2008 - 31.7 - 4.0
Repayment during the period - - - (2.4)
Balance as of
29 February 2008 1,120.9 180.3 142.7 4.0
Moreover, Rayong Real Estate Company Limited "RY" has already
informed of itsprogress of the operation for RY's immovable property
development project named Wangjuntr Golf Park project which located at 129 Moo
6 Tambol Pa Yoob Nai, Amphur Wang Chan, Ra-Yong Province. This project has
planned to develop to be a golf course with 54 holes divided into 3 phases
including club house as well as lodging and resort of which to be sold for
members and also sell some parts of land in the future. However, as the public
utility development plan approaching to the government sector has not yet
reached its target, such development therefore has been delayed and enable the
project to be not completed entirely. At present, this project has been in the
process for the specialist to have a course test for some parts especially
Phase I and Phase II zones of golf course as to prepare for its readiness and
must take some time for an official opening for the whole project. In this
regard, such development project operation has been completely operated around
the percentage of 30 of the plan. Moreover, since the opening test for service
presently has not yet received its income at the normal rate and such income
has to pay for interest to the joint ventures accordingly. However, RY has
proceeded to gradually repay interest to the joint ventures.
3) As the Company has already informed to sell the ordinary shares
of Bangkok ConcreteIndustry Company Limited (Subsidiary) "BCI" to Widen
Holding Company Limited as referred to 3), theCompany hereby informs further
concerning the loans burden of BCI with the Company as at 31 December 2007 as
detailed below.
Unit : Million Baht
Amount
Loans 111.40
Receivable interest 10.9
Receivable from sales of construction
materials and others 66.4
188.7
For the progress of repayment of BCI as above lists as at 29 February
2008 of which the Company has not yet received. However, the Company expects
to receive a repayment completed within June 2009 and such loan also has got
Widen Holding Company Limited as a whole guarantor with the Company.
Hence, kindly be informed accordingly.
Yours faithfully,
= Signature =
(Mr. Prasert Marittanaporn)
Director and Executive Vice President
: Finance and Accounting